Question 1

Activity A has a standard cost of $500 and the standard time
to complete Activity A is 5 weeks. The crash time for Activity A is 3 weeks and
the crash cost is $600. What is the crash cost per week for Activity A?

Question 1 options:

$200

$50

$150

$100

$300

Question 2

Considering the following Activity-On-Node (AON) project
(activity completion times are in days), how long will it take to complete the
project?

Click here to view a Word version of the project.

Question 2 options:

14 days

16 days

13 days

15 days

Question 3

Considering the following Activity-On-Node (AON) project
(activity completion times are in days), what is the critical path?

Click here to view a Word version of the project.

Question 3 options:

ABDF

ACDF

ABEF

ACEF

Question 4

Consider the following Activity-On-Node (AON) PERT project.
The three values that represent each activity’s completion time (in days)
correspond to an optimistic time, most likely time, and pessimistic time,
respectively. What is the expected completion time of activity A?

Click here to view a Word version of the project.

Question 4 options:

3 days

2 days

4 days

5 days

Question 5

Consider the following Activity-On-Node (AON) PERT project.
The three values that represent each activity’s completion time (in days)
correspond to an optimistic time, most likely time, and pessimistic time,
respectively. What is the standard deviation associated with the completion
time of activity B?

Click here to view a Word version of the project.

Question 5 options:

0.6667 days

0.3145 days

0.0245 days

0.3333 days

Question 6

Jamie is planning a trip overseas. A variety of activities
must be completed before her departure. The following table describes the
relationships between these activities:

Immediate

Activity
Predecessors

A –

B A

C A

D B, C

E B, C

F D, E

G F

Jamie was also able to estimate the activity times as shown
in the table below:

Activity Time
(Days)

A 4

B 4

C 5

D 3

E 3

F 2

G 1

Considering the information above, what is the slack for
activities E and F respectively?

Question 6 options:

1 day; 0 days

0 days; 1 day

0 days; 0 days

1 day; 1 day

Question 7

Consider the following set of activities that must be
completed in order to prep a new home for painting:

Immediate

Activity
Predecessors

A –

B –

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the
activity times as shown in the table below:

Activity Time
(Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the slack time
for activities E and F respectively?

Question 7 options:

0 days; 0 days

0 days; 1 day

1 day: 0 days

1 day; 1 day

Question 8

Consider the following set of activities that must be
completed in order to prep a new home for painting:

Immediate

Activity
Predecessors

A –

B –

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the
activity times as shown in the table below:

Activity Time
(Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the earliest
finish time for activity F?

Question 8 options:

16 days

12 days

14 days

10 days

Question 9

Francisco is planning a vacation to Germany. A variety of
activities must be completed before his departure. The following table
describes the relationships between these activities:

Immediate

Activity
Predecessors

A –

B –

C –

D A, B

E C

F D, E

G E

H F, G

I F

J I, H

Francisco was also able to estimate the activity times as
shown in the table below:

Activity Time
(Days)

A 3

B 4

C 5

D 3

E 2

F 1

G 4

H 3

I 2

J 5

Considering the information above, what is the slack for
activities F and G respectively?

Question 9 options:

0 days; 0 days

4 days; 0 days

4 days; 3 days

3 days; 0 days

Question 10

Francisco is planning a vacation to Germany. A variety of
activities must be completed before his departure. The following table
describes the relationships between these activities:

Immediate

Activity Predecessors

A –

B –

C –

D A, B

E C

F D, E

G E

H F, G

I F

J I, H

Francisco was also able to estimate the activity times as
shown in the table below:

Activity Time
(Days)

A 3

B 4

C 5

D 3

E 2

F 1

G 4

H 3

I 2

J 5

Considering the information above, what is the earliest
finish time for activity E?

Question 10 options:

8 days

6 days

5 days

7 days