Question 1

The critical path method diagram:

Captures all the project action items against the scheduled
timeline

Efficiently captures time on a time sensitive and large
scale project

Assesses action items and determines the best method to
accomplish them

Writes the big goals into the project time line and notes
project risk

Question 2

What is the most effective schedule development tool for
capturing the relationship of action items to the timeline?

GANTT chart

Time-scaled diagram

Milestone

Critical path method diagram

Question 3

The goal of scheduling during the early phase of project
management seeks is to:

Monitor, control, and assess cost restrictions

Summarize the project, create project goals, and define the
scope of the project

Track the project, determine personnel payments, and
allocate resources

Allocate resources, monitor, control, and track the project

Question 4

By developing a project schedule, a project manager is
planning the:

Outcomes of the project

Stakeholder management

Budget needs of the project

Time element of the project

Question 5

Which activity does the project manager use when controlling
in a project? (Select all that apply.)

Sequence

Review

Track

Revise

Build