0 Comments

Quantitative analysis:PERT and CPM.

Case Analysis

At the Hard Rock Cafe, like many organizations, project
management is a key planning tool. With Hard Rock’s constant growth in hotels
and cafes, remodeling of existing cafes, scheduling for Hard Rock Live concert
and event venues, and planning the annual Rockfest, managers rely on project
management techniques and software to maintain schedule and budget performance.

“Without Microsoft Project,” says Hard Rock
Vice-President Chris Tomasso, “there is no way to keep so many people on
the same page.” Tomasso is in charge of the Rockfest event, which is
attended by well over 100,000 enthusiastic fans. The challenge is pulling it
off within a tight 9-month planning horizon. As the event approaches, Tomasso
devotes greater energy to its activities. For the first 3 months, Tomasso
updates his MS Project charts monthly. Then at the 6-month mark, he updates his
progress weekly. At the 9- month mark, he checks and corrects his schedule
twice a week.

Early in the project management process, Tomasso identifies
10 major tasks (called level 2 activities in a work breakdown structure, or
WBS):talent booking, ticketing, marketing/PR, online promotion, television,
show production, travel, sponsorships, operations, and merchandising. Using a
WBS, each of these is further divided into a series of subtasks. The following
table identifies 26 of the major activities and subactivities, their immediate
predecessors, and time estimates. Tomasso enters all of these into the MS
Project software. Tomasso alters the MS Project document and the time line as
the project progresses. “It’s okay to change it as long as you keep on
track,” he states.

Activity

Description

Predecessor

Normal Time (weeks)

Normal Cost

Crash Time (weeks)

Crash Cost

A

Finalize site and building contracts

7

$7,500

4

$11,500

B

Select local printer

A

3

$500

2

$800

C

Hire production manager

A

3

$1,200

2

$1,700

D

Design promotional Web site

B

5

$6,000

3

$9,000

E

Set TV deal

D

6

$4,000

4

$6,500

F

Hire director

E

4

$1,200

3

$1,700

G

Plan for TV camera placement

F

2

$500

2

$500

H

Target headline entertainers

B

4

$2,000

3

$3,500

I

Target support entertainers

H

4

$2,000

3

$3,500

J

Travel accommodations for talent

I

10

$9,000

7

$16,000

K

Set venue capacity

C

2

$300

1

$400

L

Ticketmaster contract

D

3

$1,400

2

$1,900

M

On-site ticketing

L

8

$7,000

6

$11,000

N

Sound and staging

C

6

$9,000

5

$12,000

O

Passes and stage credentials

G

7

$4,000

5

$5,800

P

Travel accommodations for staff

B

20

$15,000

15

$23,000

Q

Hire sponsor coordinator

B

4

$600

3

$800

R

Finalize sponsors

Q

4

$1,000

3

$1,400

S

Define/place signage for sponsors

R

3

$3,000

2

$4,200

T

Hire operations manager

A

4

$1,200

2

$1,800

U

Develop site plan

T

6

$6,000

5

$8,500

V

Hire security director

T

7

$1,500

5

$3,000

W

Set police/fire security plan

V

4

$1,000

3

$1,600

X

Power, plumbing, AC, toilet services

U

8

$4,000

6

$7,000

Y

Secure merchandise deals

B

6

$6,000

3

$7,500

Z

Online merchandise sales

Y

6

$5,000

4

$7,500

The day of the rock concert itself is not the end of the
project planning. “It’s nothing but surprises. A band not being able to
get to the venue because of traffic jams is a surprise, but an ‘anticipated’
surprise. We had a helicopter on stand-by ready to fly the band in,” says
Tomasso.

On completion of Rockfest in July, Tomasso and his team have
a 3-month reprieve before starting the project planning process again.

Source: Professor Barry Render, Jay Heizer and Beverly Amer.

Please turn in a paper of one to two pages (page counting
does not include cover and reference list) discussing the following questions:

1. Identify the critical path and its activities for
Rockfest. How long does the project take (what is the duration time)?

2. How would you crash the project (which activities would
you crash) to keep the project on schedule and achieve the original duration,
if Activity B actually takes 5 weeks instead of the planned 3 weeks? (Explain
your logic)?

Order Solution Now

Categories: